Contains past questions for class 1 pipe construction construction management from 2020 2nd to 2011 (on-site).
*Regarding network schedule issues, the questions are for 4 years from R6 to R3, excluding R1 to H23.
This course is for those who aim to pass the exam by past exams.
There are no in-app purchases and no ads. A sample answer is included.
Start studying little by little during your commute on the train or bus or during your breaks.
*2nd year of Reiwa 6, 2nd year of Reiwa 5th, 2nd year of Reiwa 4th, 2nd year of Reiwa 3rd year, 2020, 2020, 2018, 2017, 2016, 2015, 2014, 2013, 2012, 2011
The following questions are included.
●R6~H23/○✕ Problems, improvement measures description, etc. ⇒ Examples of descriptions are provided.
●R6~H23/Notes description ⇒ Description examples are listed.
●R6-R3/Network process chart ⇒ Answers and explanations are listed.
●R6~H23/Regulations ⇒Answers are listed.
●Question 6/R5~H23/Experience description ⇒ This is for practice. An image of the answer is included.
[Example question]
Reiwa 6 [Question 1] [Question 3]
For the diagrams shown in (1) to (3), describe concretely and concisely the measures to improve the inappropriate parts.
(1) Installation instructions for single type expansion joint
(2) Pump piping procedure diagram
(3) Duct plan view
Reiwa 6 [Question 4] [Question 1]
If an absorption chiller/heater is installed in the machine room on the first floor of a five-story reinforced concrete office building and a cooling tower is installed on the roof, write the answers to the following questions 1 and 2 in the answer column.
However, matters related to process control and safety control are excluded.
Describe the following points (1) to (4) specifically and concisely in the answer column (1) to (4).
(1) Points to note from the viewpoint of maintenance management regarding the arrangement of absorption chiller/heater
(2) Points to note from the perspective of maintenance management regarding piping construction around the absorption chiller/heater
(3) Notes regarding the foundation of cooling towers
(4) Notes on piping construction around the cooling tower
Reiwa 6 [Question 4] [Question 2]
Describe the characteristics of an absorption chiller/heater specifically and concisely in answer column (1).
In addition, in answer column (2), please specifically and concisely describe the technical matters that you consider particularly important to carry out during the period from the installation of the equipment on the foundation to the start of the comprehensive trial run adjustment of the entire air conditioning system.
However, matters related to question 1 are excluded.
Reiwa 6 [Question 5] [Question 1]
If a drinking water tank (an FRP panel tank) is installed in the water tank room on the first floor of a 5-story reinforced concrete office building and stainless steel pipes for general plumbing are used for the water supply pipes, write the answers to Questions 1 and 2 below in the answer column.
However, matters related to process control and safety control are excluded.
Describe the following points (1) to (4) specifically and concisely in the answer column (1) to (4).
(1) Points to note from the perspective of maintenance management regarding the arrangement of water receiving tanks
(2) Points to note regarding piping construction around the water tank
(3) Points to note when joining stainless steel pipes for general piping
Reiwa 6 [Question 5] [Question 2]
Describe the characteristics of the FRP panel tank specifically and concisely in answer column (1).
In addition, in (2) of the answer column, write specifically and concisely the technical matters that you consider particularly important to implement regarding the tank after installation.
However, matters related to question 1 are excluded.
Reiwa 6 [Question 2] [Question 1]
(4) Points to note when supporting stainless steel pipes for general piping with steel hardware
In the network schedule shown in the figure below, write the answers to the following questions 1 to 5 in the answer column. However, A to K between events in the diagram represent the work content, and the number of days represents the number of work days.
Answer the route of the critical path in the form of connecting event numbers with → (dammies are dashed arrows).
Reiwa 6 [Question 3] [Question 1]
In the text regarding work involving asbestos, etc., select and fill in the words, phrases, or numerical values specified in the "Industrial Safety and Health Act" that apply to [A] to [C] from the selection column.
(1) For indoor workplaces where dust such as asbestos is emitted, the employer must, in principle, install equipment to seal off the source of the dust, [A] or push-pull type ventilation system.
(2) The employer must have the asbestos work chief inspect [A] push-pull ventilation systems, dust removal equipment, etc. every period not exceeding [B] months.
Reiwa 6 [Question 3] [Question 2]
Describe the words and phrases specified in the Industrial Safety and Health Act that apply to [D] and [E] in sentences regarding occupational safety and health at construction sites.
(1) When an employer employs workers to perform work related to erecting, dismantling, or changing scaffolding (excluding auxiliary work on the ground or on a solid floor), the employer must carry out [D] for safety or health related to the work.
(2) When performing work using an aerial work vehicle (excluding those with a structure in which the work floor rises or descends only perpendicular to the ground surface), the employer must have workers on the work floor of the said aerial work vehicle use the required performance [E], etc.
*We make every effort to ensure that the point explanations and writing examples in the app are as accurate as possible, but please note that we do not necessarily guarantee accuracy. We will not be held responsible for any inconvenience or disadvantage caused by using this application.